最新的HPE Network Data Center Professional Architect - HPE7-A12免費考試真題
問題1
What is a key advantage of an active-active dual-homed server NIC design using VSX/MC-LAG at the access layer compared to active-standby NIC teaming?
What is a key advantage of an active-active dual-homed server NIC design using VSX/MC-LAG at the access layer compared to active-standby NIC teaming?
正確答案: A
說明:(僅 PDFExamDumps 成員可見)
問題2
Which two items are typically part of a "gap analysis" performed after the current state assessment? (Choose two.)
Which two items are typically part of a "gap analysis" performed after the current state assessment? (Choose two.)
正確答案: A,E
說明:(僅 PDFExamDumps 成員可見)
問題3
Your customer requires management access to switches through SSH. Which authentication mechanism can be implemented?
Your customer requires management access to switches through SSH. Which authentication mechanism can be implemented?
正確答案: C
說明:(僅 PDFExamDumps 成員可見)
問題4
You are modernizing a customer's legacy three-tier architecture with an L3 spine and leaf topology. The CX switches in the topology will provide the overlay. The customer data center uses six VRFs. The customer has asked for service leaf switches to connect to two clustered firewalls, which route and filter traffic between the VRFs. How can you maximize the efficiency of the traffic flow between subnets in the same VRF?
You are modernizing a customer's legacy three-tier architecture with an L3 spine and leaf topology. The CX switches in the topology will provide the overlay. The customer data center uses six VRFs. The customer has asked for service leaf switches to connect to two clustered firewalls, which route and filter traffic between the VRFs. How can you maximize the efficiency of the traffic flow between subnets in the same VRF?
正確答案: D
說明:(僅 PDFExamDumps 成員可見)
問題5
You have successfully installed, configured, and migrated the customer to the new Aruba CX data center equipment. What documents are normally part of the post-installation deliverables?
You have successfully installed, configured, and migrated the customer to the new Aruba CX data center equipment. What documents are normally part of the post-installation deliverables?
正確答案: D
說明:(僅 PDFExamDumps 成員可見)
問題6
Waratah Hospital, based in Australia, is planning to move many data center services to new facility. (The remaining legacy data center will not be part of this project.) Waratah Hospital hired an external consultant to assist with the new data center network design.
Based on the requirements for the data center network infrastructure, the external consultant has created a high-level design. The below summarizes the content of the design document.
Requirements and information:
- Six racks in the data center room (single row).
- Redundant Top of Rack leaf switches with back-to-front cooling in each rack, providing 10/25 Gbps connectivity to servers, storage, and other devices.
- Four 100 GbE uplinks per leaf switch.
- The customer requested to install all switch ports facing the back of the rack racks (hot aisle.)
- OOB management for servers, storage, and network has to be provided through an external switch with back-to-front cooling. This switch has to be included in the solution. One OOB switch provides connectivity for two racks.
- Core equipment for the OOBM network is being reused.
- Middle-of-row spine switches.
-The data center should connect to the hospital building with links that provide 400 Gbps.
- Internet access is provided through an existing firewall cluster with two firewalls, each firewall in one data room. The second firewall is operating in standby mode, VRRP is utilized on the firewalls for failover. The data center network should connect to these firewalls with links that total
100 Gbps.
- The external link is a dark fiber direct link based on single-mode fiber (OS2). The distance to the main hospital 1.5 KM. The links will terminate on two core switches in the hospital.
The customer also requires:
- 99.999% uptime for this life-critical environment.
- Planned and unplanned downtime has to be minimized.
- Software upgrades are only allowed once per year with close to zero downtime.
- All life-critical resources are accessed locally, and all resources exist within the hospital campus.
- Waratah Hospital requires a highly secure environment for the data center. Encrypted wire speed connectivity between the data room and the hospital is a must-have because the link between the buildings crosses a public road.
- Waratah Hospital has a mix of virtualized (vSphere) servers. Nutanix storage, bare metal servers, backup servers and other devices.
In the past, the hospital has had a security breach that resulted in data loss, network downtime, and identity theft.
What are valid assumptions that can be made for this scenario when creating the network design documentation? (Choose two.)
Waratah Hospital, based in Australia, is planning to move many data center services to new facility. (The remaining legacy data center will not be part of this project.) Waratah Hospital hired an external consultant to assist with the new data center network design.
Based on the requirements for the data center network infrastructure, the external consultant has created a high-level design. The below summarizes the content of the design document.
Requirements and information:
- Six racks in the data center room (single row).
- Redundant Top of Rack leaf switches with back-to-front cooling in each rack, providing 10/25 Gbps connectivity to servers, storage, and other devices.
- Four 100 GbE uplinks per leaf switch.
- The customer requested to install all switch ports facing the back of the rack racks (hot aisle.)
- OOB management for servers, storage, and network has to be provided through an external switch with back-to-front cooling. This switch has to be included in the solution. One OOB switch provides connectivity for two racks.
- Core equipment for the OOBM network is being reused.
- Middle-of-row spine switches.
-The data center should connect to the hospital building with links that provide 400 Gbps.
- Internet access is provided through an existing firewall cluster with two firewalls, each firewall in one data room. The second firewall is operating in standby mode, VRRP is utilized on the firewalls for failover. The data center network should connect to these firewalls with links that total
100 Gbps.
- The external link is a dark fiber direct link based on single-mode fiber (OS2). The distance to the main hospital 1.5 KM. The links will terminate on two core switches in the hospital.
The customer also requires:
- 99.999% uptime for this life-critical environment.
- Planned and unplanned downtime has to be minimized.
- Software upgrades are only allowed once per year with close to zero downtime.
- All life-critical resources are accessed locally, and all resources exist within the hospital campus.
- Waratah Hospital requires a highly secure environment for the data center. Encrypted wire speed connectivity between the data room and the hospital is a must-have because the link between the buildings crosses a public road.
- Waratah Hospital has a mix of virtualized (vSphere) servers. Nutanix storage, bare metal servers, backup servers and other devices.
In the past, the hospital has had a security breach that resulted in data loss, network downtime, and identity theft.
What are valid assumptions that can be made for this scenario when creating the network design documentation? (Choose two.)
正確答案: A,B
說明:(僅 PDFExamDumps 成員可見)