問題1
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a.Any deviation from the procedures described in the test
b.strategy document
c.The overall estimated costs, timescales and resource
d.requirements
e.A detailed schedule of testing activities
f.The development deliverables to be tested
g.Which test staff members (names) will be involved and when
h.Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a.Any deviation from the procedures described in the test
b.strategy document
c.The overall estimated costs, timescales and resource
d.requirements
e.A detailed schedule of testing activities
f.The development deliverables to be tested
g.Which test staff members (names) will be involved and when
h.Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
正確答案: D,F
說明:(僅 PDFExamDumps 成員可見)
問題2
Explain how the above mentioned report may differ from a report that you produce for the project manager, who is a test specialist Select TWO items from the following options that can be used to report to the project manager and would not be included in a report to senior management. 1 credit
Explain how the above mentioned report may differ from a report that you produce for the project manager, who is a test specialist Select TWO items from the following options that can be used to report to the project manager and would not be included in a report to senior management. 1 credit
正確答案: B,E
問題3
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
正確答案: B
問題4
Considerable attention will be given in this project to defining exit criteria and on reporting back on their status. Which combination of TWO exit criteria from the list would be best to use? 1 credit
I. Total number of defects found
II. Percentage of test cases executed
III. Total test effort planned versus total actual test effort spent
IV.
Defect trend (number of defects found per test run over time
Considerable attention will be given in this project to defining exit criteria and on reporting back on their status. Which combination of TWO exit criteria from the list would be best to use? 1 credit
I. Total number of defects found
II. Percentage of test cases executed
III. Total test effort planned versus total actual test effort spent
IV.
Defect trend (number of defects found per test run over time
正確答案: C
說明:(僅 PDFExamDumps 成員可見)
問題5
Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk? 3 credits
Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk? 3 credits
正確答案: B
問題6
In addition to introducing the new team member, you have decided to raise motivation. Which of the measures listed below would be the best measure to take in order to increase the motivation of the team? 2 credits
In addition to introducing the new team member, you have decided to raise motivation. Which of the measures listed below would be the best measure to take in order to increase the motivation of the team? 2 credits
正確答案: C
問題7
As part of the improvement program, the organization is also looking at tool support. Which type of tool could be used to ensure higher quality of the code to be reviewed? 1 credit
As part of the improvement program, the organization is also looking at tool support. Which type of tool could be used to ensure higher quality of the code to be reviewed? 1 credit
正確答案: B