最新的Microsoft TS: Microsoft Project Server 2010, Configuring - 70-177免費考試真題
問題1
You have a Project Server 2010 environment. You need to configure a new category for a resource manager that allows the manager to manage only the current and future resources that are subordinate to the manager in the organization chart. You create a new category. What should you do next?
You have a Project Server 2010 environment. You need to configure a new category for a resource manager that allows the manager to manage only the current and future resources that are subordinate to the manager in the organization chart. You create a new category. What should you do next?
正確答案: C
問題2
You have a Project Server 2010 environment. You need to configure a Project Server instance so that only one month of future assignments is displayed on the My Tasks page. You do not need to display all tasks. What should you do?
You have a Project Server 2010 environment. You need to configure a Project Server instance so that only one month of future assignments is displayed on the My Tasks page. You do not need to display all tasks. What should you do?
正確答案: C
問題3
You have a Project Server 2010 environment. You need to configure Project Server to allow members of the maintenance crew to choose their work assignments from a shared list. What should you do?
You have a Project Server 2010 environment. You need to configure Project Server to allow members of the maintenance crew to choose their work assignments from a shared list. What should you do?
正確答案: B
問題4
You are upgrading from Project Server 2007 to Project Server 2010. You need to ensure that only Project Professional 2010 client computers can connect to Project Server 2010. What should you do?
You are upgrading from Project Server 2007 to Project Server 2010. You need to ensure that only Project Professional 2010 client computers can connect to Project Server 2010. What should you do?
正確答案: B
問題5
You have a Project Server 2010 environment. A developer creates, tests, and deploys a workflow to the farm. You need to make the workflow available in Project Web App (PWA). Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You have a Project Server 2010 environment. A developer creates, tests, and deploys a workflow to the farm. You need to make the workflow available in Project Web App (PWA). Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
正確答案: B,C
問題6
You have a Project Server 2010 environment. A team leader has accidently approved a proposed project. You need to allow the team leader to reject the proposed project, while making sure the project is listed on the monthly Rejected Proposed Project report. What should you do?
You have a Project Server 2010 environment. A team leader has accidently approved a proposed project. You need to allow the team leader to reject the proposed project, while making sure the project is listed on the monthly Rejected Proposed Project report. What should you do?
正確答案: D
問題7
You have a Project Server 2010 environment. You create a custom view to display a list of delayed projects. You need to make sure that only senior managers in your company have access to the custom view. What should you do?
You have a Project Server 2010 environment. You create a custom view to display a list of delayed projects. You need to make sure that only senior managers in your company have access to the custom view. What should you do?
正確答案: A
問題8
You have a Project Server 2010 environment. You need to create a backup plan that will
allow you to rebuild your Project Server environment in the event of a total system loss. What should you do?
You have a Project Server 2010 environment. You need to create a backup plan that will
allow you to rebuild your Project Server environment in the event of a total system loss. What should you do?
正確答案: D